Join Our Email Alerts-Subscribe
Important Note:Login & Check Your Email Inbox and Activate Confirmation Link



Enter Your Email :

Copyright Disclaimer:
Section 107 of the Copyright Act Fair Use Contents .
We are forwarding content link(s) from our website to content website & We are not serving any contents.
Main Source:Google.com.All the Content PDF link(s) is/are obtained from GoogleSearch
for the purpose of Education & Teaching Intention. Not for commercial purpose.
Technicalsymposium.com is not liable/responsible for any copyright issues.

Placement Materials & Answers-Free Download


Software Companies Placement Papers With Answers-Amdocs -Free Download

1. It was calculated that 75 men could complete a piece of work in 20 days. When work was scheduled to commence, it was found necessary to send 25 men to another project. How much longer will it take to complete the work?

Answer:

30 days.

Explanation:

Before:

One day work

= 1 / 20

One man’s one day work = 1 / ( 20 * 75)

Now: No. Of workers = 50

One day work = 50 * 1 / ( 20 * 75)

The total no. of days required to complete the work = (75 * 20) / 50 = 30

2. A student divided a number by 2/3 when he required to multiply by 3/2. Calculate the percentage of error in his result.

Answer:

0 %

Explanation:

Since 3x / 2 = x / (2 / 3)

3. A dishonest shopkeeper professes to sell pulses at the cost price, but he uses a false weight of 950gm. for a kg. His gain is …%.

Answer:

5.3 %

Explanation:

He sells 950 grams of pulses and gains 50 grams.

If he sells 100 grams of pulses then he will gain (50 / 950) *100 = 5.26

4. A software engineer has the capability of thinking 100 lines of code in five minutes and can type 100 lines of code in 10 minutes. He takes a break for five minutes after every ten minutes. How many lines of codes will he complete typing after an hour?

Answer:

250 lines of codes

5. A man was engaged on a job for 30 days on the condition that he would get a wage of Rs. 10 for the day he works, but he have to pay a fine of Rs. 2 for each day of his absence. If he gets Rs. 216 at the end, he was absent for work for ... days.

Answer:

7 days

Explanation:

The equation portraying the given problem is:

10 * x – 2 * (30 – x) = 216 where x is the number of working days.

Solving this we get x = 23

Number of days he was absent was 7 (30-23) days.

6. A contractor agreeing to finish a work in 150 days, employed 75 men each working 8 hours daily. After 90 days, only 2/7 of the work was completed. Increasing the number of men by¬¬ ________ each working now for 10 hours daily, the work can be completed in time.

Answer:

150 men.

Explanation:

One day’s work = 2 / (7 * 90)

One hour’s work = 2 / (7 * 90 * 8)

One man’s work = 2 / (7 * 90 * 8 * 75)

The remaining work (5/7) has to be completed within 60 days, because the total number of days allotted for the project is 150 days.

So we get the equation

(2 * 10 * x * 60) / (7 * 90 * 8 * 75) = 5/7 where x is the number of men working after the 90th day.

We get x = 225

Since we have 75 men already, it is enough to add only 150 men.

7. What is ‘a’ percent of ‘b’ divided by ‘b’ percent of ‘a’?

(a) a (b) b (c) 1 (d) 10 (d) 100

Answer:

(c) 1

Explanation:

a percent of b : (a/100) * b

b percent of a : (b/100) * a

a percent of b divided by b percent of a : ((a / 100 )*b) / (b/100) * a )) = 1

8. A man bought a horse and a cart. If he sold the horse at 10 % loss and the cart at 20 % gain, he would not lose anything; but if he sold the horse at 5% loss and the cart at 5% gain, he would lose Rs. 10 in the bargain. The amount paid by him was Rs.¬¬¬-_______ for the horse and Rs.________ for the cart.

Answer:

Cost price of horse = Rs. 400 & the cost price of cart = 200.

Explanation:-

Let x be the cost price of the horse and y be the cost price of the cart.

In the first sale there is no loss or profit. (i.e.) The loss obtained is equal to the gain.

Therefore (10/100) * x = (20/100) * y

X = 2 * y -----------------(1)

In the second sale, he lost Rs. 10. (i.e.) The loss is greater than the profit by Rs. 10.

Therefore (5 / 100) * x = (5 / 100) * y + 10 -------(2)

Substituting (1) in (2) we get

(10 / 100) * y = (5 / 100) * y + 10

(5 / 100) * y = 10

y = 200

From (1) 2 * 200 = x = 400

Source: Contents are provided by Technicalsymposium Google Group Members.
Disclaimer: All the above contents are provided by technicalsymposium.com Google Group members.
Further, this content is not intended to be used for commercial purpose. Technicalsymposium.com is not liable/responsible for any copyright issues.



Download-Placement Paprs & Answers PDF


Free Placement Study Notes PDF-Download



Technicalsymposium.com- Fresher Jobs & All Study Notes-Free Download










Technicalsymposium.com-Free Live Support-Chat with Our Experts

Official Contact: +91-9245556793 (Whatsapp Message / SMS / Voice Call)


Our Expert team is ready to answer all your questions immediately-Feel free to speak in Tamil/English.

(Example:Events info/Lecture Notes/Off-Campus & All Jobs/Projects & All education information)

Working hrs (IST): (Morning: 10:00AM-3:00 PM) and (Evening:5:00 PM to 10:00 PM)

All Latest Question & Answer Page (FAQ)-Click here